- SV < 0 or SPI < 1: Behind schedule (e.g., SPI = 0.80 means progressing at 80% of planned rate).
- SV > 0 or SPI > 1: Ahead of schedule.
- Estimated Duration:
Planned Duration / SPI.
"EVM Brings Sanity to Software Projects"
Why EVM Matters (Not Too Fast, Not Too Slow)
Comparing AC vs. PV alone lies to you! Only comparing EV against both PV (schedule) and AC (cost) reveals true project health in money and time.
How Far Are We From Plan? SV, CV, SPI, CPI
- CV < 0 or CPI < 1: Over budget! (e.g., CPI = 0.889 means getting $0.89 of value per $1 spent).
- CV > 0 or CPI > 1: Under budget (cost efficient).
- Notice:
EVis ALWAYS first in every variance & numerator in SPI/CPI!
Forecasting Completion: EAC, ETC, VAC, TCPI
1. Typical Variance (DEFAULT if unspecified)
Things are off-track and will continue at current CPI efficiency:EAC = BAC / CPI
2. Atypical Variance (One-Off Blip)
Overspend was a once-off problem; remaining work executes at planned rate:EAC = AC + (BAC − EV)
3. Combined Cost & Schedule (CPI & SPI)
When both schedule & cost efficiency drive final cost:EAC = AC + (BAC − EV) / (CPI × SPI)
4. Bottom-Up Re-Estimate
Original plan invalid; add new bottom-up cost:EAC = AC + New Bottom-Up ETC
Estimate to Complete (ETC)
ETC = EAC − AC → How much money is still left to spend from now to finish.
Variance at Completion (VAC)
VAC = BAC − EAC → At the end, did we save (+) or overrun (−)?
To-Complete Performance Index (TCPI)
TCPI = (BAC − EV) / (BAC − AC) → Efficiency required on remaining dollars to hit original BAC (>1 means harder than planned).
School Portal Case: Month 5 of 10
Given Baseline Data (Customer School Portal)
Planned Duration = 10 months • Current Time = Month 5 • BAC = $400k • PV = $200k • EV = $160k • AC = $180k
| Metric | Calculation | Result | PM Meaning (Required in Exam!) |
|---|---|---|---|
| SV & SPI | 160k − 200k | 160 / 200 |
-$40k | 0.80 |
Behind schedule by $40,000 of work; progressing at 80% speed. |
| CV & CPI | 160k − 180k | 160 / 180 |
-$20k | 0.889 |
Over budget by $20,000; earning only $0.89 value per $1 spent. |
| EAC (Typical) | 400k / 0.8889 |
$450,000 |
Forecasted final total cost of the project. |
| ETC | 450k − 180k |
$270,000 |
Remaining cash needed to complete the portal. |
| VAC | 400k − 450k |
-$50,000 |
Projected to finish $50,000 over original budget. |
| TCPI | (400−160)/(400−180) = 240/220 |
1.091 |
Must deliver $1.09 value per remaining $1 to stay inside $400k BAC. |
| Est. Duration | 10 months / 0.80 |
12.5 months |
2.5-month schedule overrun unless corrective action is taken. |
Explain the Numbers Like a PM
- Mr Bhuru warns: Expect questions asking "What does that mean? What does it mean for you as a PM?"
- Always state both the dollar/index figure AND whether the project is ahead/behind or under/over budget.
- Always use
EAC = BAC / CPIunless the question says the overspend was a "one-off" (Atypical) or asks to use both SPI & CPI.
- "Don't speculate things" — compute directly from EV, PV, AC, and BAC earned milestones.
- Remember: calculations sit on the Hard exam question!
Completed Concept 6: Earned Value Management
Next up: Risk Management (Exposure, Prompt Lists, Trees, Cycle) & Resource Allocation.